Check the piping lines for correctness of such as pressure, flows or pressure
loss, if the hydraulic pipe once are installed in the base machine.
A pressure control valve has to be installed, if there is no pressure control
valve on the main control valve of base machine.
Be careful so that dust may not enter the hydraulic breaker and base
machine.
Install or remove the hydraulic breaker on horizontal ground without mud
or dust
Be careful so that dust may not enter the hydraulic breaker and base
machine.
Install or remove the hydraulic breaker on horizontal ground without mud
or dust
If the bucket cylinder is retracted,
the installation will be easier.
3) Move the base machine in the vicinity of hydraulic
breaker, and align the pin hole of arm with the pin
hole of hydraulic breaker, and then, insert the pins.
4) After the arm pin is inserted, lift the boom, insert
the hydraulic breaker on the wood blocks like 4-3-3.
Extend the bucket cylinder, fit it to the bucket link’s
hole and insert the pins.
5) Install the stop rings, align the bolt holes and insert
the bolts, mutually lock double nut.
If the stop rings are secured with one nut only, the
service life of the bolt may be shortened or the bolt
may be loosened out very quickly.
6) Stop the engine of the base machine, turn off the
main switch and discharge the air pressure in the
hydraulic oil tank.
7) Remove the union caps from the hydraulic breaker
pipe of the arm end, and connect the hoses after
disassembling the hose plug.
If the stop rings are secured with one nut only, the
service life of the bolt may be shortened or the bolt
may be loosened out very quickly.
6) Stop the engine of the base machine, turn off the
main switch and discharge the air pressure in the
hydraulic oil tank.
7) Remove the union caps from the hydraulic breaker
pipe of the arm end, and connect the hoses after
disassembling the hose plug.
Model
Hose
Diameter
(inch)
Length
(mm)
Working
Pressure
(bar)
45/53/68/75 1/2 1450 140
85/100 3/4 1850 170
135/140(A) 1 2300 180
150/155 1 2500 180
165(F) 1-1/4 2800 190
175 1-1/4 3000 200